Saturday, June 20, 2015

Construction - Month 17 - Interior Paint, Kitchen cabinets, Staircase

Month 17 (Weeks 65-68)

This month, more work finished as we made our commitment to move in. That date approaches fast and thus trying to get enough of the house in order to move in has quickly become the priority.

The painter finished priming, painting, and sanding the door and window trim.



Also the interior doors..




The drywall repair guy came back to patch up all the drywall areas that had to be cut into for various reasons such as the ceiling in the family room to access the plumbing leading to the tub..



The electrician came and installed most of the remaining plugs and switches. Also the WAC lighting that we put into the staircase, install a light in the powder room and adding power to the hot water heaters so those would work.

I worked on the kitchen cabinets deciding to install those.. My brother and I - after much debate on measurements and how to do it (don't get two engineers to install cabinets unless you want to hear a debate) - installed the wall cabinets. Then the next day I worked alone installing the base cabinets and island. Pretty fun work I thought.. Not that physically hard but lots to think about to make sure things are plumb and your walkways are even and everything is just right. Once the counter-tops go in there isn't any opportunity to move things.





The staircase company showed up at the end of the month and started installing the stairs. The painter primed the balusters first and then the false ends and baseboards went in. We're going with a maple that we think will match our hardwood flooring choice that'll need to be stained. Also we found a newel post on houzz that we loved and asked them to duplicate. Can't wait to see it!




We've also been having a problem with the front and rear door strike plates in that the way i did the trim, they're not long enough. The door locking mechanism makes contact with the trim instead of the strike plate causing damage. So I had to get a custom strike plate fabricated for the rear door at a sheet metal machine shop since Anderson doesn't sell custom strike plates. The front door is getting a custom one from Baldwin who do sell custom ones.




We've been having some issues with the HVAC system. Apparently one of the condensers needed a new coil even though it's new. Must've been a lemon batch. The other one mysteriously keeps losing power. I'll walk up to the thermostat and the screen will be dead. Both got fixed which is a relief since temperatures have climbed into the 80's and even 90's.

We've also been spending a lot more time cleaning of late. for good reason..

Next month we scramble to complete as much as possible in the midst of moving in.. yikes! As you can see by the above, there is MUCH to do yet.


Friday, June 19, 2015

Construction - Month 16 - Master bath, fireplace, and interior trim paint prep

Month 16 (Weeks 61-64)

The house limped along this month.. I didn't do much work myself since I was sick one weekend, out of town another weekend running a half marathon (ouch! finished in my usual 2 hours or so), and went on a business trip one week.



But I still managed to hang some headers upstairs and we are mostly done with window and door trim at this point. There are a few stragglers which I can't do until they repair the drywall around the box beams in the master bedroom.



The master bath tub arrived on site. The master bath made a lot of progress and most of it got finished. The tub and tub filler was installed, the shower glass arrived and was installed, the mirrors went in, the sinks, the faucets, the hanging lighting went in. 






The tile guys also grouted everything.. The master bath floor and shower, the powder room wall, the master bath pebbles on the wall.

They also installed the fireplace stone in the master bedroom.. We think it looks great!



Electrical made more progress and is almost done. In fact we submitted the form for our electrical smart meter and I paid the fee for it which means we're a a couple of week away from the house getting on permanent power and the construction fence coming down.

The two tankless systems went in.. here is the one on the outside




The kitchen cabinets arrived from cabinets.com. We had to unbox everything and inspect it so that we could request replacement parts if anything was amiss. There were some doors we didn't like how they turned out but mostly everything looked good.




We decided to hire the painter who did the outside to spray the inside trim and all the doors so that it would look as good as possible (no brush marks). This is a pretty big hit to our budget ($10k) but i think will be worth it in the long run. His team spent about a week and a half prepping everything for the spraying.. Caulking, filling nail holes, taping windows and putting paper on drywalls.






Lastly, we did a walkthrough with our builder and gave him a list of follow up items since his work on the project is done. The rest is up to us to do