Wednesday, April 29, 2015

Construction - Month 15 - Master bath, electrical fixtures and fans, kitchen start

Month 15 (Weeks 57-60)

The house limps along.. Someone told me recently that once you get to drywall, you're only halfway done. Boy were they right..

This month we saw a whole bunch of electrical fixtures go in (all the remaining ones). This is primarily the ceiling lights in the laundry room, staircase, upstairs closet, and a whole lot of ceiling fans.


pergola fans.. wet rated


family room fan


bedroom/office fans


master bedroom fan (we're not crazy about it)


staircase lighting

The powder room got it's feature wall tiled after we figured out what light fixture we were putting in there and realized we had to change the wiring from two fixtures on each side of the mirror to a single overhead fixture. Some drywall destruction and cables being moved later, the wall got floated and tiled..


The master bathroom made progress! They figured out the radiant floor problem and repaired it. They then tiled it and installed the vanity. The Vanity got it's Caeserstone countertop as did the shower wall and curb. The Hubberton Forge lighting got put in and the frames for the mirrors went in as well. All that's left now is the sinks, faucets/plumbing, tub, toilet, shower glass, and mirrors which should wrap up next month.


flooring tile and pebble grout


hubbarton forge lighting, mirror frames, and pebble accent


custom vanity


shower floor and curb/wall tops in caeserstone



shower shampoo niche

Meanwhile we built more headers and footers and caulked them for upstairs. Then installed them.. 

I also got some plywood for the kitchen cabinets to sit on after some trauma going to three different Home Depots because the first two's saw was out of order.


future base/wall cabinet locations

I then measured and sketched out the kitchen layout in preparation for installing the cabinets when they arrive in the coming weeks. Thankfully the measurements all seem to be working and lining up with everything.. E.g. everything plays out from the center of the kitchen sink window and things like the peninsula's lighting and the range's hood exit line up perfectly. It would've sucked if something major was off this late in the game.. Even the electrical cables coming out of the wall for the under counter lighting and in-cabinet lighting appear to be in the right place.




Lastly, we passed our electrical inspection which is huge since it means we PG&E will now permanently hook up the house to power. No more having only 30 amps of power for the whole house and now the fence can come down since the house can be locked up.

Tuesday, April 7, 2015

Construction - Month 14 - Laundry Room, Master Bedroom & Bath, HVAC

Month 14 (Weeks 53-56)

The master bathroom made some progress.. Namely they caulked the shower and feature wall tile and our custom master bedroom vanity has finally been completed! It arrived along with the mirror frames and toilet shelves that were done in the same style.




Unfortunately while all that did happen, the installation of it all sat and for two weeks nothing happened. The radiant heat floor was still damaged and they haven't been able to repair it so everything sits until they figure that out. Frustrating.. it's been damaged for 6-7 weeks.



The laundry room floor was also tiled and caulked with the tile we chose that resembles hardwood flooring.


Lastly, the HVAC guy showed up and they installed the two condensers and replacement thermostats so everything is working now.


In the meantime and while they didn't get much work done, I got a lot of work done. I built out the french doors on the lower and upper floor and the master bedroom to get them ready for trim installation..


We also completed the majority of trim that was left downstairs by building, caulking, and hanging over 20 headers and footers. The downstairs is starting to look a lot more complete..


I then turned my attention upstairs where I ripped through the remaining vertical pieces of material that I had installing them on the majority of the upstairs doors and windows..